Project Milestones


Initial specifications and work programme (MS1)
Work Packages involved: 1,5
Expected date: April 2011
Means of validation: D1.1, D5.1

First results in view of the MYRRHA consolidated design (MS2)
Work Packages involved: 2, 4, 5
Expected date: January 2012
Means of validation: D2.1, D4.1, D5.2

Survey of the status of the MYRRHA linac consolidated design (MS3)
Work Packages involved: 1, 2, 3, 4, 5
Expected date: October 2012
Means of validation: D1.2, D2.2, D4.2, D5.3 and Mid-term design review

First MAX final reports (MS4)
Work Packages involved: 1, 2, 3, 4
Expected date: July 2013
Means of validation: D1.3, D1.4, D2.3, D3.1, D3.2, D4.3

MAX key final reports (MS5)
Work Packages involved: 1, 2, 3, 4, 5, 6
Expected date: January 2014
Means of validation: D1.5, D2.4, D3.3, D4.4, D4.5, D5.4, D6.1 and final design review

 